View County-maintained roads in repair due to storm damage
Last update: 03/04/2024 - 15:47
2023 Storm damage repair projects
Links in the road name column will direct to location-specific pages with additional information. Some pages are still under development and will become available in the near future.
*The list below does not include emergency work or closure due to work performed by utility companies
No. | Road Name (alphabetical) | Description of Damage | Proposed Repair | Repair Status | Road Status | Construction Schedule |
1 | Aldercroft Heights Road Site 1 | Landslide | Construct retaining wall, restore road | Design consultant selection | Road open to traffic. | TBD |
2 | Aldercroft Heights Road Site 2 | Slipout | TBD | Design consultant selection | Road open to traffic. | TBD |
3 | Alma Bridge Road | Partially failed culvert and slope erosion | Replace culvert Reconstruct road section | Evaluation | Road open to traffic. | TBD |
4 | Bear Creek Road Site 1 | Road Undermined Failed Culvert | Replace culvert, install downstream junction box/manhole replace debris rack reconstruct road section | Complete | Road open to traffic. | Complete |
5 | Bear Creek Road Site 2 | Sink hole | Replace culvert, reconstruct road section | Evaluation | Road currently subject to one lane closure with stop traffic control | TBD |
6 | Bear Creek Road Site 3 | Slipout | Construct retaining wall, restore road | Evaluation | Road currently subject to one lane closure with stop traffic control | TBD |
7 | Black Road Site 1 | Slipout | Stabilize slope with shotcrete and soil nails, restore road | Complete | Road open to traffic. | Complete |
8 | Calaveras Road Site 1 | Slipout | Replace culvert, stabilize slope | Evaluation | Road open to traffic. | TBD |
9 | Clayton Road | Landslide | Construct retaining wall, restore road | Pre-Design | Temporary gravel access has been re-established subject to one-lane stop control | Permanent repair TBD. |
10 | Hicks Road Site 1 | Slipout | TBD | Evaluation | Road currently subject to one lane closure with stop traffic control | TBD |
11 | Hicks Road Site 2 | Slipout | TBD | Evaluation | Road open to traffic. | TBD |
12 | Hicks Road Site 3 | Slipout | TBD | Evaluation | Road open to traffic. | TBD |
13 | Kincaid Road Site 1 | Uphill landslide | Clear remaining landslide debris | Complete | Road open to traffic. | Work complete. |
14 | Kincaid Road Site 2 | Slipout | TBD | Evaluation | Road currently subject to one lane closure with stop traffic control | TBD |
15 | Mines Road Site 1 | Road washed out | Replace culvert Reconstruct road section | Substantially Complete | Road open to traffic. | Roadway construction substantially complete. Related closeout activities are ongoing. |
16 | Mines Road Site 2 | Culvert failure | Replace culvert Reconstruct road section | Substantially Complete | Road open to traffic. | Roadway construction substantially complete. Related closeout activities are ongoing. |
17 | Mines Road Site 3 | Slipout | TBD | Evaluation | Road open to traffic. | TBD |
18 | Montebello Road | Shoulder erosion | TBD | Evaluation | Road open to traffic. | TBD |
19 | Mount Madonna Road | Slipout | Construct retaining wall, restore road | Evaluation | Road currently subject to one lane closure with stop traffic control | TBD |
20 | Old Santa Cruz Highway Site 1 | Road Slipout Failed Culvert | Construct retaining wall, replace culvert, restore road | Evaluation | Full Road Closure. | Permanent repair TBD |
21 | Old Santa Cruz Highway Site 2 | Slipout | Stabilize slope with shotcrete and soil nails, restore road | Substantially Complete | Road open to traffic | Roadway construction substantially complete. Related closeout activities are ongoing. |
22 | Old Santa Cruz Highway Site 3 | Slipout | Construct retaining wall, restore road | Evaluation | Road open to traffic. | TBD |
23 | Old Santa Cruz Highway Site 4 | Shoulder slipout | Construct retaining wall, restore road | Evaluation | Road open to traffic. | TBD |
24 | On Orbit Drive | Slipout | TBD | Evaluation | Road open to traffic. | TBD |
25 | Quimby Road | Roadway settling | TBD | Evaluation | Road open to traffic. | TBD |
26 | San Antonio Valley Road Site 1 | Slipout | Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road | Construction On-going | Road currently subject to one lane closure with stop traffic control | Substantial completion targeted early 2024 |
27 | San Antonio Valley Road Site 2 | Slipout | Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road | Pre-construction | Road currently subject to one lane closure with stop traffic control | Substantial completion targeted early 2024 |
28 | San Antonio Valley Road Site 3 | Slipout | Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road | Construction On-going | Road currently subject to one lane closure with traffic signal control | Wall construction complete, final paving and close-out activities on-going |
29 | San Antonio Valley Road Site 4 | Slipout | Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road | Design | Road currently subject to one lane closure with stop traffic control | Early 2024 |
30 | San Antonio Valley Road Site 5 | Slipout | Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road | Pre-construction | Road currently subject to one lane closure with stop traffic control | Construction beginning March 2024 |
31 | Weller Road | Culvert failure | Replace culvert | Evaluation | Road open to traffic. | TBD |
32 | West Road | Slope erosion | Stabilize slope with shotcrete and soil nails | Substantially Complete | Road open to traffic. | Roadway construction substantially complete. Related closeout activities are ongoing. |
33 | Willow Springs Rd | Undermining | Rebuild embankment, restore roadway | Evaluation | Road open to traffic. | TBD |