Project location
San Antonio Valley Road approx. 3.3 mi east of Lick Observatory (approx. 0.5 mi east of MM 3)
Project description
A slipout resulted in the loss of the westbound lane. The permanent repair will involve the construction of a retaining structure and the restoration of the roadway. One tree will be removed.
Project timeline
- Damage identified: Late January 2023
- FEMA inspection: Early April 2023
- Construction begin: Late September 2023
- Construction complete: Anticipated Spring 2024
Current status
Construction on-going
Project documents (reports, plans, etc.)
Pending