Project location
San Antonio Valley Road approx. 6.7 mi east of Lick Observatory (near MM 7)
View the location mapView the proximity map
Project description
A slipout resulted in the loss of the eastbound lane. The permanent repair will involve construction of a retaining structure, replacement of the cross-road culvert, and restoration of the roadway.
Project timeline
- Damage identified: Early March 2023
- FEMA inspection: Early September 2023
- Construction begin: March 2024 (weather dependent)
- Construction begin: Anticipated spring 2024
Current status
Pre-construction activities
Project documents (reports, plans, etc.)
Pending