Project location
Weller Road approx. 2.5 mi north of Calaveras Road
View the Location map
Project description
High storm flows resulted in debris blocking the culvert and causing the roadway to be overtopped and embankment headcutting to occur. Internal culvert damage has also resulted in embankment erosion undermining the roadway. The permanent repair will involve replacement of the culvert.
Project timeline
- Damage identified: Late March 2023
- FEMA inspection: Early September 2023
- Consultant retained: Anticipated Spring 2024
- Design work initiated: Anticipated Spring 2024
- Exploratory activities: TBD
- Design finalized: TBD
- Project advertised: TBD
- Contract awarded: TBD
- Construction start: TBD
- Construction complete: TBD
Current status
Pending design consultant selection
Project documents (reports, plans, etc.)
FEMA Final Public Notice
Project point of contact