Project location
Mines Road approx. 6.8 mi north of San Antonio Valley Rd/Del Puerto Canyon Rd junction (approx. 0.3 mi north of MM 26)
View the location mapView the Proximity map
Project description
A culvert failure resulted in the washout of the entire road section. The permanent repair involves the replacement of the culvert and restoration of the roadway.
Project timeline
- Damage identified: Early January 2023
- Road closed: Early January 2023
- Construction start: Early February 2023
- Road re-opened: Late February 2023
- FEMA inspection: Early April 2023
- Final paving: Mid-October 2023
Current status
Final close-out activities on-going.
Project documents (reports, plans, etc.)
FEMA final public notice
Project point of contact
[email protected]